What unplanned downtime really costs a plant (it's more than the machine rate)

Most plants undercount downtime by pricing it at the machine's hourly rate. The real cost includes lost margin, idle crews, overtime, expediting and penalties. Here is how to count it.

ManufacturingPublished 3 minute read

Key points

  • The machine's hourly rate captures only one part of a stop. Lost contribution margin is usually the largest, and labour, overtime, expediting and penalties add to it.
  • Count five cost lines for every stop: lost margin, idle labour, recovery overtime, expediting and customer credits.
  • Test the method on one line for a month, then present a range to leadership instead of a single precise number.

Why the hourly rate undercounts

A common shortcut is to multiply the stopped hours by the machine's running cost per hour. It is quick, and it produces a number that looks official, but it leaves out most of what a stop actually does to the business.

A stop takes units you could have sold, keeps people standing by, forces overtime later, sometimes means buying freight to catch up, and can trigger a late-delivery credit. Each of these has a different owner in the company, which is why the full cost often goes unseen.

The five costs to count

  • Lost contribution margin: units not made multiplied by the margin each unit would have earned, not by its selling price.
  • Idle labour: the loaded cost of the crew that waited during the stop.
  • Recovery overtime: the cost of making back some of the lost units on overtime.
  • Expediting: premium freight or rush supplier charges needed to protect a delivery.
  • Customer credits and scrap: late-delivery credits, penalties, and product scrapped during restart.

A worked example (illustrative numbers)

Assume a line that makes 1,200 units an hour, earns a contribution margin of $4 per unit, and has a crew of six at a loaded rate of $35 an hour. A 45-minute stop costs roughly this:

Cost lineWorkingAmount
Lost contribution margin900 units × $4$3,600
Idle labour6 people × 0.75 h × $35$158
Recovery overtime450 units recovered at 1.5× rate$118
ExpeditingRush freight on one late order$850
Total per stopabout $4,700

A machine-rate estimate would count only the margin line, about $3,600 here. The stop costs about 30% more once the other lines are included. If this line stops twice a week for 50 working weeks, the annual cost is in the region of $470,000, which is the figure a leadership team can act on.

How to make the number credible

  • Use your own rates. Contribution margin, crew cost and recovery rates vary a lot between plants. Replace the example numbers before you show anyone.
  • Count stops by reason. A total is less useful than knowing which three reasons account for most of the lost time.
  • Show a range. Present a low and high estimate with the assumptions written down. A range that is honest about its inputs is easier to trust than a single precise figure.
  • Track it for a month first. One month of consistent stop reasons will reveal more than a year of estimates.

Where to start

Our downtime cost calculator applies the same logic to your own inputs. If your numbers show a meaningful cost, the next step is to find which stop reasons account for most of it. The 30-day method for finding your biggest production losses covers that in detail.